30 พฤษภาคม 2546
COMMERCIAL OPERATION OF ROI ET GREEN PLANT
No. EGCO 350/211
Date : May 30, 2003
Attn : President of the Stock Exchange of Thailand
Subject: Commercial Operation of Roi ET Green Power Plant
Reference is made to the periodical report to the Stock Exchange of Thailand
on the progress of Roi Et Green Power Project.
Electricity Generating Public Company Limited (EGCOMP) would like to inform
the SET that Roi ET Green Power Plant with 8.8 MW capacity commercially operated
on May 29, 2003. Its whole capacity is supplied to Electricity Generating
Authority of Thailand (EGAT) under 21-year Power Purchase Agreement.
Yours sincerely,
Kraisi Karnasuta
President